CJ Industries were awarded the contract to design and construct a new 6000 M2 yard area for Moana Orchards in Tasman, Motueka. In order to accommodate the grower’s seasonal time-frame the project had varying time constraints around certain elements. CJ Industries handled the complete job including to:
- Excavate 6500 M3 of clay material
- Level and contour clay to form plant able area for new orchard
- Retain clay bank with rock filled gabion baskets
- Design and construct stormwater drainage system
- Design and construct a 2000m2 concrete apron
- Construct 4000m2 metal bin store and yard
Check out our similar case studies:
Champion Road Subdivision
CJ Industries were awarded the contact at 134 Champion Rd to build a 20-lot subdivision. CJ Industries completed all works from start to finish. Scope of works included excavation and filling of 25,000m3 of clay to build roads and house platforms. This was a challenging site because of the site’s close proximity to an earthquake fault line and weak soil structures. Each lot required the...
See Project
Daelyn Drive Subdivision
CJ Industries were awarded the contract to build a 16-lot subdivision at 10 Daelyn Drive Nelson and completed all works from start to finish including: GPS set out and machine control Bulk earthworks All drainage work including sub soil, sewage, stormwater and reticulated water Connection to council reticulated system Facilitation of power and communication contractors Nib and Kerb & channel Exposed aggregate concrete thresholds and...
See Project
Check out our related products: