Case Studies

Tahunanui Beach Carpark
CJ Asphalt were awarded the contract by Downer supply and lay 25mm asphalt to overlay the existing failing chip sealed car park area at the Tahunanui beach. The scope included: Site setout Milling of existing high areas and key into existing kerb and channel Asphalt pre-levelling Supply and apply an emulsion tack-coat Supply and lay of 25mm of asphalt to the prepared pavement
See Project
Chip Seal Driveway with Swale Drain
This 120m long driveway required grading to shape with a crossfall into a 300mm deep swale drain. CJI Quarry basecourse was supplied, placed and compacted to ensure a sturdy base. A challenge of this project was the steep grade of the driveway, CJI safely and efficiently completed the project which delivered a long-term solution for the client access to their property.
See Project
Fairfield Coolstore Slabs
CJ Industries were approached to construct two new concrete slabs to accommodate cold stores for an orchard.  CJ Industries was the obvious fit for this job as we looked after the complete project from removing orchard trees right through to finishing the concrete slab. The scope included: Remove orchard trees Strip topsoil and stockpile Construct sub-base with certified CJ Industries quarry rock Setout slab lines...
See Project
Richmond West Berryfield Subdivision Stages 4A-9
CJ Industries commenced work on Stage 4A of this Berryfield Subdivision in May 2020. Due to the successful outcome of this project and the relationships formed with the client and engineers this led on to a further five stages totaling over 300 Sections continuing to November 2023. This project helps address the growing need for housing in the Richmond Community. Tasks involved with these projects...
See Project
Commercial Building Earthworks
CJ industries were awarded the contract to complete earthworks and civil construction for two new commercial buildings in Central Nelson. The projects location is classed as a HAIL site and is listed on the Hazardous Activities and Industries List therefore requiring the extracted fill to be tested for contamination before it could be reused for the building’s seismic rafts. Scope included:  Site set-out Liaison between...
See Project
Falcon Brae – Stonefly Lodge
CJ Industries were awarded the contract to complete earthworks and road formation at a new 5 star luxury fishing lodge in the Motueka Valley. This project was completed over 3 years in a challenging location with the need to consider many sub-contractor movements all working to a tight schedule: The scope of this project: Erosion and sedimentation management Compliance with Resource Consent conditions Excavate and...
See Project
Inglis Packers Concrete Slabs
CJ Industries were approached to construct multiple concrete slabs to accommodate a packhouse extension, new cold stores and drive-thru canopies.  CJ industries completed the project from start to finish by removing orchard trees to clear the site right through to finishing the concrete slab and grouting the steel columns. The scope included: Remove orchard trees Strip topsoil and cart to waste Construct sub-base with certified...
See Project
Kaiteri Road Construction
CJ Industries won the contract to construct a new road into a private right of way in Kaiteriteri, Abel Tasman. The scope included: Arborist work clearing native and pine trees Cutting a new road through granite rock Supply and installation of culvert pipes Constructing a new road to local council specification from CJ’s certified basecourse and top course  
See Project
Mitre 10 Demolition
CJ Industries were awarded the demolition of the local Mitre 10 Motueka and construction of the new building foundations and car park. Scope included: Demolition of existing buildings and sort materials for recycling Excavate building foundations and prep new building floor with laser machine control Construct pavement for new asphalt car park including kerb and channel and dish channel and concrete panel retaining construction. Construction...
See Project
Moana Orchards
CJ Industries were awarded the contract to design and construct a new 6000 M2 yard area for Moana Orchards in Tasman, Motueka.  In order to accommodate the grower’s seasonal time-frame the project had varying time constraints around certain elements.   CJ Industries handled the complete job including to: Excavate 6500 M3 of clay material Level and contour clay to form plant able area for new orchard...
See Project
Motueka Quay Driveway
CJ Industries looked after the design and construction of a new driveway in Motueka Quay. This was a high-profile job incorporating multiple styles of concrete and required a very high standard finish. When the driveway design was finalised CJ Industries set to work installing drainage and kerb and channelling.  The surfaces were then prepped and finished in coloured exposed aggregate concrete.  The last item to...
See Project
Residential Asphalt Driveway
In this project CJ Asphalt were approached to find a solution to up-grade an existing failing residential chip seal driveway on the Richmond hills. CJ Asphalt handled everything in the project including: Earthworks Supply, level and compact AP40 Construction for passing bays and turnaround area Rock drainage swale Wooden edging Asphalt preparation Supply and lay 30mm Asphalt to the prepared pavement The result was outstanding...
See Project
Saltwater Creek Bridge
CJ Industries were the civil works contractor on the award Saltwater Creek Bridge Replacement Project for the Nelson City Council. We provided the onsite project management as well as traffic management which involved the challenge of working adjacent to the main road and the entrance to Nelson city and a very tight site construction area. Other challenges included critical time-lines, pedestrian management and sediment control...
See Project
TRS Nelson AC Driveway
CJ Asphalt were awarded the contract to construct a new 3000 M2 Asphalt yard suitable for tractors and farm implements for TRS new offices and workshop on the Appleby Highway in Richmond, Nelson. The scope included: Site setout Supply, level and compact AP40 Pavement construction Construction of 40mm Asphalt on a grade 5 membrane seal to the prepared surface
See Project
TDC Road Realignment
CJ Industries were awarded the contract to realign the road on the Motueka Valley Highway. The scope included: Site set–out Temporary creek diversion Traffic management Quarry suitable rock for river erosion control Installation of box culvert Line river bank with rock Construct 2 coat chip–seal road to NZTA standard
See Project
TDC Road Construction
CJ Industries were contracted by Downer to reconstruct the access road into the Dovedale Water Scheme source which was affected by Cyclone Gita.  This involved clearing and reforming over 5km of road including installation of culvert pipes, fluming and forming of new water tables.
See Project
Tasman Driveway
CJ Industries helped this client with an overhaul of his driveway. The scope includes: Earthworks Formation of driveway and finish in Riwaka gold chip and 2 coat chip seal Construction of concrete drainage swale Supply and level 13mm Riwaka Gold chip on turning area
See Project
Saxton Fruit – Building Slab
CJ industries were contracted to construct earthworks, drainage and concrete slab for Saxton Fruit in Nelson. The scope included: Installation of stormwater, sanitary sewer and reticulated water for new building Supply level and compact sub-base Installation of precast retaining wall Supply and install formwork, reinforcing mesh and tie Supply place and cure 2500 M2 concrete floor slab Expansion cutting Form and finish 2 coat chip-seal...
See Project
Orchard Tracks
CJ industries have had a long involvement in roading whether it be a gravel orchard track, a road into a new house site, often finished in a 2 coat chip seal, asphalt or concrete surface. This job involved putting in several kilometres of new road around a local hop orchard. The scope included: Excavation of unsuitable material Supply, level and compact AP65, AP40 and AP20...
See Project
NPD ST Vincent St
CJ Industries were elected head Civil Contractor to build the new NPD Fuel Station in Nelson central. There was a critical path that had to be meet on this job which involved the station being open before a certain date which was achieved. The scope was comprehensive and involved the following: Demolition of existing structures Earthworks Civil and drainage construction Traffic and pedestrian management Excavation...
See Project
Motueka NW Water Reticulation
CJ Industries were appointed as the Head Contractor for this TDC contract C1130 to install reticulated water in the North- Western area of Motueka. This was a comprehensive job involving multiple crews, managing traffic, excavation of trenching, installing and testing reticulation, testing and quality control of water systems and reinstatement of the road. The scope included: – GPS set-out and machine control – Excavation of...
See Project
Kaiteri Castle Demolition
CJ Industries won the contract for a deconstruction and demolition of “The Castle” over-looking the Abel Tasman National Park.   This project took over a month and involved navigating into a difficult entrance with machinery as well as trucks which removed over 1000m3 materials to be recycled  and to waste.
See Project
Gravel Driveway Marahau
This Project involved refurbishing a pre-existing 2km long driveway. To enhance drainage, culverts were incorporated, and a layer of CJI Quarry AP40 was provided, laid, and compacted for the final finish. The driveway had experienced significant degradation over numerous years due to adverse weather conditions. CJ Industries implemented a sustainable remedy, ensuring the driveway’s resilience against future weather events for the client.
See Project
Highland Drive Subdivision
CJ Industries were awarded the contact at 134 Champion Rd to build a 20-lot subdivision.  CJ Industries completed all works on this project from start to finish. This scope of work included excavation and filling of 25,000m3 of clay to build roads and house platforms.  This was a challenging site because of its proximity to an earthquake fault line and weak soil structures.  Each lot...
See Project
Goldpine Concrete Slabs
CJ industries have been contracted to construct a variety of concrete slabs around the Goldpine Post Production site in Kohatu, Nelson.  Over the past 3 years we have been involved with the following projects: Drainage construction of 100mm, 225mm, 300mm PVC pipes sumps and manholes Construction of approx. 5000 M2 of external concrete slab reinforced with fibre mesh Construction of fuel tank, fuelling foundations and...
See Project
Golden Bay Fruit Packers
Apollo Projects contracted CJ Industries to complete various parts of the new Golden Bay Fruit packers complex in Motueka.  CJ Industries supplied over 4000 m3 of concrete and had a construction team work on elements of the building and site. This project has over 2 hectares under cover! The scope included: Supply of over 4000 M3 of certified premix concrete Construction of external concrete slabs...
See Project
Daelyn Drive Subdivision
CJ Industries were awarded the contract to build a 16-lot subdivision at 10 Daelyn Drive Nelson and completed all works from start to finish including: GPS set out and machine control Bulk earthworks All drainage work including sub soil, sewage, stormwater and reticulated water Connection to council reticulated system Facilitation of power and communication contractors Nib and Kerb & channel Exposed aggregate concrete thresholds and...
See Project
Champion Road Subdivision
CJ Industries were awarded the contact at 134 Champion Rd to build a 20-lot subdivision. CJ Industries completed all works from start to finish. Scope of works included excavation and filling of 25,000m3 of clay to build roads and house platforms. This was a challenging site because of the site’s close proximity to an earthquake fault line and weak soil structures. Each lot required the...
See Project